MP-26-13 — Utility Substation in conjunction with data center expansion in Alpharetta, GA
This case seeks a master plan amendment, conditional use permit, and variance to allow a Georgia Power utility substation on a 38.8-acre data center property. The request includes reducing an undisturbed buffer, amending security fence materials and height to 22 feet (exceeding the standard 8-foot limit), and proposes screen walls on both the subject property and across the street on Georgia Power property to minimize visual impacts.
| Case number | MP-26-13 |
|---|---|
| Type | PD Amendment |
| Location | 4905 North Point Parkway |
| County | Fulton County |
| Parcel / legal | Land Lots 850, 851, 858 & 859, 1st District, 2nd Section, Fulton County, Georgia |
| Acreage | 38.8 |
| Proposed use | Utility Substation in conjunction with data center expansion |
| Petitioner | Royal 400 Data Center |
| Owner | Georgia Power |
| Hearing | 2026-11-05 |
| Hearing body | Planning Commission Meeting November 2026 |
| Staff recommendation | approve with conditions |
| Record | Updated after it was first seen; not a decision |
The summary and fields above are read automatically from the agenda packet, so they can be wrong or incomplete — the packet itself is the record. Tell us if something here is wrong.
Property & nearby activity
Case history
Every time this case appeared on an agenda we watched, and what changed.
- First seen — 2026-08-21: First seen on a Planning Commission Meeting September 2026 agenda · Planning Commission Meeting September 2026
- Staff recommendation: Staff recommendation: none stated · Planning Commission Meeting September 2026
- Hearing scheduled — 2026-10-01: Hearing scheduled for 2026-10-01 · Planning Commission Meeting October 2026
- Continued — 2026-11-05: Continued from 2026-10-01 to 2026-11-05 · Planning Commission Meeting November 2026
- Staff recommendation — 2026-11-05: Staff recommendation: approve with conditions · Planning Commission Meeting November 2026
Also on the 2026-11-05 Alpharetta agenda
- V-26-06 — Rezoning
- WI-0338 — Other
- 350 Wills Lane Enclave - Site Plan — Residential site development
- 4905 North Point Parkway - Utility Substation — Utility Substation
Other Alpharetta rezoning cases
P&Z Radar AI agent · Expand
Hi, I’m Pip. How can I help?