MP-26-13 — Utility Substation in conjunction with data center expansion in Alpharetta, GA

This case seeks a master plan amendment, conditional use permit, and variance to allow a Georgia Power utility substation on a 38.8-acre data center property. The request includes reducing an undisturbed buffer, amending security fence materials and height to 22 feet (exceeding the standard 8-foot limit), and proposes screen walls on both the subject property and across the street on Georgia Power property to minimize visual impacts.

Case numberMP-26-13
TypePD Amendment
Location4905 North Point Parkway
CountyFulton County
Parcel / legalLand Lots 850, 851, 858 & 859, 1st District, 2nd Section, Fulton County, Georgia
Acreage38.8
Proposed useUtility Substation in conjunction with data center expansion
PetitionerRoyal 400 Data Center
OwnerGeorgia Power
Hearing2026-11-05
Hearing bodyPlanning Commission Meeting November 2026
Staff recommendationapprove with conditions
RecordUpdated after it was first seen; not a decision

View the source agenda PDF →

The summary and fields above are read automatically from the agenda packet, so they can be wrong or incomplete — the packet itself is the record. Tell us if something here is wrong.

Property & nearby activity

Case history

Every time this case appeared on an agenda we watched, and what changed.

Also on the 2026-11-05 Alpharetta agenda

Other Alpharetta rezoning cases

Tracking this case? P&Z Radar emails you when cases like this appear on a covered Atlanta P&Z agenda — ahead of the hearing where the city posts ahead. Start a free trial.